Notice: Star Route Road TRIS Reconstruction Project

The Star Route Road TRIS Reconstruction Project, which will repair 2.2 miles of road, is currently taking place with a potential completion date of August 1st.  The contractors involved in the project have stated their intention to keep at least one lane open for local traffic as much as possible, but there will be times between 8AM and 3PM when the road will need to be closed completely to replace culverts.  Please allow for delays or take an alternate route whenever possible.  For residents of the road: workers on site may be able to provide specific information about the culvert replacement schedule on a day-to-day basis and provide updated information about whether access to your home may be affected.  Please check with them if it is safe to do so.  

Thank you for your understanding.